The dependency map — deprecated after one day

A cross-link of every internal document to its stream, its open questions and what needed a human — written on 18 May, marked DEPRECATED on 19 May, and never updated again. The thing that replaced it froze too.

Original title
Internal Document Dependency Map
Original date
18 May 2026
Project phase
Stage 1 — after the first community meeting
Purpose at the time
Cross-link the internal documents to workplan streams, surface open questions, and separate what needed human action from what needed more research.
Status at the time
Marked DEPRECATED on 19 May 2026, one day after it was written, in favour of a generated synthesis layer. Never updated after that.
Source provenance
Derived from internal/dependency-map.md (private working corpus; unpublished, unchanged).
Publication treatment
Substantially intact
Derived / prepared by
Claude (Fable 5) with Adrian Wedd, 18 August 2026
Prepared
2026-08-18
Human review
Adrian Wedd — publication review completed 19 August 2026
Published
2026-08-19
What was changed for publication
  • The previous prospective purchaser is described by role, not named — consistently with assumptions-register.md (AR-09) and with the public meeting transcript, which anonymised him as "a prospective purchaser" at the time. He is a private individual whose purchase did not proceed; the reported price, the documents he shared and the meeting-reported status of both are kept in full.
  • Published substantially intact, including its own deprecation notice.
  • The insolvency firm is referred to as 'the appointed receivers'.
  • Included precisely because it was superseded after a day. The generated layer that replaced it — current-state.md — froze on 19 May and was wrong when it froze; see [the state machinery](/archive/state-machinery/). A project that replaces a hand-maintained map with an automated one, and then loses both, is a common enough story that it is worth having the evidence for it.
  • The per-person version of this map, which assigns work to named individuals, is permanently withheld under carve-out 6.

Document begins

Internal Document Dependency Map

Date: 18 May 2026 | Last synced: 2026-05-18 | Internal only — not for public release. Purpose: cross-link existing internal docs to workplan streams, surface open questions, and identify what needs human action vs further research.


DEPRECATED — 2026-05-19. This file is a historical snapshot. It is no longer updated. The synthesis brief (internal/synthesis/current-state.md, generated by scripts/synthesize_state.py) is the live reconciliation layer. GitHub issues are the work ledger. Refer to those, not this file.

Document Index

FileOwned by StreamStatusPrimary consumer
workplans.mdSteering committeeAuthoritative — steering review pendingAll streams
working-groups.mdSteering committeeAligned with workplans — use togetherAll streams
finance_assumptions_book.mdStream 3Draft v0.1 — steering review required before use in modellingStream 3, Stream 6
property_status_check.mdStream 1Desk research only — several TODOs require human browser checkStream 1, Stream 3
heritage_desktop_research.mdStream 4 (WP 4.2)Desk research complete — works classification table readyStream 4, Stream 6
lawyer_brief_draft.mdStream 2Draft ready — placeholder fields (name/date/contact) need filling before sendingStream 2
liquor_licensing_reform_status.mdStream 2Desk research only — one manual parliament check outstandingStream 2
legal_licensing_brief.mdStream 2Background research — feeds lawyer briefStream 2
finance_assumptions_book.md → Section 6Stream 320 unpopulated inputs listed — each maps to a stream task belowStream 3, Stream 4, Stream 6
epics/EPIC-001-*.mdStream 5 / SteeringStage discipline and public messaging audit tasksStream 5, Steering
epics/EPIC-002-*.mdStream 2Legal structure and co-op rules options — feeds lawyer_brief_draft.mdStream 2
epics/EPIC-003-*.mdStream 2Liquor licensing pathway — feeds liquor_licensing_reform_status.mdStream 2
epics/EPIC-004-*.mdStream 3Financial model and capital stack — feeds finance_assumptions_book.mdStream 3
epics/EPIC-005-*.mdStream 2 / Stream 6Governance architecture — fed by Stream 2 structure decisionStream 2, Stream 6
epics/EPIC-006-*.mdResearch CellCase study and evidence base verification tasksResearch Cell, all streams
epics/EPIC-007-*.mdSteeringDue diligence and decision gates — stage-gate roadmapSteering, Stream 6

GitHub issues: Access to adrianwedd/bottom-pub-coop was unavailable at last sync — no issue cross-references confirmed. Re-check when access is restored.


Stream-to-Document Map

Stream 0 — Steering Committee Formation

No document yet. Outputs needed: conflict-of-interest protocol, authorised receivers-contact appointment, decision log template. These are human governance tasks, not research tasks.

Task status:

TaskStatusNotes
0.1 Call formation meetingUNBLOCKEDBillie has the ~12 names. Can happen immediately
0.2 Agree conflict-of-interest protocolUNBLOCKEDPrerequisite for seating anyone — do before task 0.3
0.3 Fill six skill seatsUNBLOCKED — depends on 0.2Convenor, legal/governance, hospitality/licensing, heritage/building, comms, finance
0.4 Appoint authorised contact for the appointed receiversBLOCKED-BY-HUMAN — most urgent outputNo agent can do this. One named person with authority. Blocks all of Stream 1
0.5 Agree public-language sheetUNBLOCKEDCan be drafted immediately; needs steering committee ratification
0.6 Set up decision log and fortnightly check-inUNBLOCKEDSimple shared document — can start today
0.7 Decide on interim entity before co-op registersBLOCKED-BY-STREAM (Stream 2 legal advice)Do not decide until Stream 2 delivers
0.8 Transition steering committee to elected boardBLOCKED-BY-STREAM (Stream 2 co-op formation timing)Stage 2+

Blocking everything else: Task 0.4 (appoint authorised contact for the appointed receivers). Until this is done, Stream 1 is stalled on tasks 1.1 and 1.6+.


Stream 1 — Property Status & Liaison

Primary doc: property_status_check.md

Task status:

TaskStatusNotes
1.1 Re-establish the receivers contactBLOCKED-BY-HUMAN (task 0.4)Cannot happen without authorised contact from Stream 0
1.2 Log all communicationsUNBLOCKEDSet up the log file now, populate as contact happens
1.3 Desktop property research (Heritage, zoning, title)UNBLOCKED — partially doneproperty_status_check.md covers most of this; open TODOs below
1.4 Confirm title structureBLOCKED-BY-HUMAN — needs title searchCosts money; steering group decision to fund
1.5 Request the previous purchaser’s asbestos/building reportsBLOCKED-BY-HUMANBillie mentioned access — needs human follow-up
1.6 Request physical building accessBLOCKED-BY-HUMAN (task 0.4 + 1.1)Authorised contact makes this request once contact re-established
1.7 Research conditional offer requirementsUNBLOCKED (desktop/legal research) — but BLOCKED-BY-STREAM (Stream 2) for designResearch what conditions are legally possible; no offer design yet

Open questions from property_status_check.md:

  • HUMAN CHECK REQUIRED (high priority): Visit commercialrealestate.com.au/for-sale/cygnet-tas-7112/hotel-leisure/ — Google’s index shows one hotel/leisure listing for Cygnet; unknown if it’s the Commercial Hotel.
  • Check realestate.com.au and domain.com.au manually (blocked scraping).
  • Check specialist hotel brokers: HTL Property, CBRE Hotels, JLL Hotels, Savills Hotels.
  • Search ASIC published notices for “Commercial Hotel Cygnet” or “Cygnet Hybrid Trust.”
  • Search Heritage Tasmania online register for Place ID 3472 — confirm current Works Applications.
  • Title search: LPI/Land Tasmania — confirm whether commercial building and ~0.5 ha residential land is single title or separable. (Feeds assumptions book 1.5, 1.6; feeds Stream 3 capital model.)

Stream 3 dependency: Section 6, item 6.1 (receiver asking price) cannot be populated until authorised contact is made. Section 6, item 6.2 (title structure) requires a title search.


Primary docs: lawyer_brief_draft.md, legal_licensing_brief.md, liquor_licensing_reform_status.md Related epics: EPIC-002 (legal structure options), EPIC-003 (liquor licensing pathway), EPIC-005 (governance architecture)

Task status:

TaskStatusNotes
2.1 Research and compare legal structuresUNBLOCKEDInitial desk research done in briefings; turn into decision matrix
2.2 Map Tasmanian liquor licensing pathwayUNBLOCKED — mostly doneliquor_licensing_reform_status.md + EPIC-003 cover this; one parliament check outstanding
2.3 Prepare structure decision brief for steering groupUNBLOCKEDDepends on 2.1 research completing; can draft in parallel
2.4 Draft professional advice briefUNBLOCKEDlawyer_brief_draft.md is substantively ready
2.5 Research interim entity optionsUNBLOCKEDDesktop research — urgent given property timeline
2.6 Deliver structure recommendationBLOCKED-BY-STREAM (2.3 brief + legal opinion)Needs lawyer; steering committee must decide
2.7 Draft CNL-compliant co-op rulesBLOCKED-BY-STREAM (task 2.6 decision)Do not draft rules until structure is settled
2.8 Prepare member/formation disclosure pathwayBLOCKED-BY-STREAM (task 2.6 decision)Distributing co-op only; legal review required
2.9 Advise on membership frameworkBLOCKED-BY-STREAM (task 2.6 decision)Tied to structure choice

lawyer_brief_draft.md — the brief is substantively ready. It:

  • Frames the distributing/non-distributing binary correctly (s.18 vs s.19 CNL)
  • Flags the earlier draft’s illegal straddle (returns + asset lock in the same instrument)
  • Covers CCU legality, ASIC overlap, membership classification, and the employed-manager liquor licence pathway
  • Has placeholder fields: [Name, Role], [DATE], [Email/Phone] — HUMAN ACTION required to fill and send

Open questions surfaced in the brief itself:

  • A1: Distributing vs non-distributing — written legal opinion required
  • A2: Can a non-distributing co-op issue debentures paying interest? (The CNL provisions are complex here)
  • A3: Confirm the earlier straddle is unlawful — get written confirmation for the record
  • B1: Who can hold the liquor licence? (s.22 natural person requirement)
  • B2: Associate scrutiny under s.3A — every co-op board director is an associate of the licensee

liquor_licensing_reform_status.md — one outstanding check:

  • HUMAN CHECK: Open parliament.tas.gov.au bills register and search “Liquor Licensing” — confirm whether any amending bill has been introduced or passed. If the reform has passed, the employed-manager pathway analysis changes materially.

Stream 3 dependency: Assumptions book Section 6, item 6.19 (structure choice) blocks all capital instrument design. Lawyer opinion is the prerequisite.

Stream 6 dependency: Operating model cannot be finalised until liquor licence pathway is confirmed (employed-manager model vs direct co-op licence).


Stream 3 — Finance & Capital Feasibility

Primary doc: finance_assumptions_book.md Related epic: EPIC-004 (financial model and capital stack)

Task status:

TaskStatusNotes
3.1 Build assumptions bookUNBLOCKED — in progressfinance_assumptions_book.md draft v0.1 exists; 20 unpopulated inputs listed
3.2 Model capital stack under both structure scenariosUNBLOCKED (scenario modelling) — BLOCKED-BY-STREAM (Stream 2) for instrument designRun both distributing/non-distributing scenarios now with placeholder ranges; finalise once Stream 2 decides
3.3 Map grant eligibility by structure typeUNBLOCKEDDesktop research; no dependencies
3.4 Compile available capital instruments under Tasmanian lawUNBLOCKEDDesktop research; site’s capital pathways briefing is a starting point
3.5 Assess residential land separabilityUNBLOCKED (desktop/planning research) — BLOCKED-BY-HUMAN for definitive answerTitle search and planning check needed for confirmation
3.6 Design specific capital instrumentsBLOCKED-BY-STREAM (Stream 2 structure decision)Cannot design a debenture without knowing the legal constraints
3.7 Update EOI to gauge non-binding interest levelsBLOCKED-BY-STREAM (Stream 5 EOI channel; Stream 3 frames questions)Stream 5 asks; Stream 3 designs the questions. Hold until steering group approves wording
3.8 Run sensitivity analysisBLOCKED-BY-STREAM (task 3.1 assumptions book)Run once 3.1 is sufficiently populated

The assumptions book is the canonical financial register. Its Section 6 lists 20 unpopulated inputs. Mapping each to the stream that unblocks it:

ItemWhat’s neededUnblocked by
6.1Receiver asking price or valuationStream 1 authorised contact + independent valuer
6.2Title structure (single/separable)Stream 1 title search
6.3Residential land valueStream 1 (title) + registered valuer
6.4Independent building condition reportStream 4 + physical access
6.5Minimum viable opening scopeStream 4 + independent assessment
6.6Heritage architect scope and costStream 4 task 4.4
6.7BCA/DDA compliance assessmentStream 4 task 4.5
6.8Asbestos removal/management costStream 1 (get existing report) + licensed assessor
6.9Award-compliant staffing modelStream 6 task 6.3
6.10Insurance premiumsBroker quotes — after venue configuration defined
6.11UtilitiesTasmanian benchmarks + building condition report
6.12Annual liquor licence feeTreasury Tasmania fee schedule (public — human check)
6.13Music licensing costsAPRA AMCOS + PPCA tariff schedules (public — human check)
6.14Council ratesHuon Valley Council
6.15Grant eligibility by structureDepends on 6.19 (structure choice)
6.16Bank lending pre-approvalDepends on legal formation + governance track record
6.17Co-op formation costsScoped legal brief → written legal opinion
6.18ACNC charity registration feasibilitySpecialist charity law advice
6.19Distributing vs non-distributingSteering committee decision after Stream 2 delivers legal opinion
6.20F&B revenue benchmarksATO benchmarks + hospitality consultant

The two items that are actually “human check now, costs nothing”: 6.12 and 6.13. Both sources are public. No professional required.


Stream 4 — Building, Heritage & Planning

Primary doc: heritage_desktop_research.md

Task status:

TaskStatusNotes
4.1 Collate existing material (the previous purchaser’s reports, the local builder’s verbal assessment)UNBLOCKED — partially doneVerbal assessment captured in meeting transcript; Billie has access to reports (human follow-up needed to retrieve)
4.2 Desktop heritage research — works classification tableUNBLOCKED — COMPLETEheritage_desktop_research.md desk research complete; works classification table ready
4.3 Define minimum viable opening scopeBLOCKED-BY-HUMAN (physical access)Cannot be done without building walkthrough
4.4 Scope independent structural and building condition assessmentUNBLOCKEDGet quotes; prepare brief; do not commission yet
4.5 Research BCA/DDA compliance requirementsUNBLOCKEDDesktop research; Class 6 heritage requirements are publicly available
4.6 Commission independent building assessmentBLOCKED-BY-HUMAN (funding + physical access from Stream 1)Depends on task 4.4 scope, steering group funding approval, Stream 1 physical access
4.7 Map staged capital works sequence with cost rangesBLOCKED-BY-HUMAN (task 4.6 commissioned assessment)Needs formal condition report as basis

The works classification table (9 categories) is complete. Key findings already resolved:

  • Heritage tier: State [FACT] — confirmed from Heritage Tasmania datasheet. The property is permanently registered at State level (not National). This resolves the meeting-transcript ambiguity.
  • Curtilage: Whole of Title [FACT] — any ground works within the title area requires heritage approval.
  • No Statement of Significance [FACT] — places listed prior to 2007 did not receive one. A Conservation Management Plan should be prepared by a heritage architect to address this gap before major works.
  • Later additions [FACT] — the register description explicitly notes “later additions to each side.” These may be non-significant fabric, allowing simpler approval pathways for works to those sections. Requires Heritage Council confirmation.

Open questions from this doc:

  • Task 4.3: Define minimum viable opening scope — the single most important building output for the business plan. Cannot be done without physical access.
  • Task 4.4: Scope independent structural and building condition assessment — get quotes before commissioning.
  • Task 4.6: Commission assessment — depends on Stream 1 physical access.
  • Heritage architect: Which fabric in the original double-storey section is “significant” vs which later additions are “non-significant”? The answer changes the approval category and cost for multiple works items.

Stream 6 dependency: The minimum viable opening scope (task 4.3) is the critical input to the path-to-profitability model (Stream 6, task 6.6). Stream 6 cannot produce a meaningful model without it.


Stream 5 — Community & Communications

Related epic: EPIC-001 (stage discipline and public messaging)

Task status:

TaskStatusNotes
5.1 Update EOI databaseUNBLOCKED~68 names; Billie has the list. Add meeting sign-ups, remove duplicates
5.2 Run skills and interest inventoryUNBLOCKEDMap 68 EOI contacts against stream skill needs
5.3 Open non-Facebook channelsUNBLOCKEDEmail newsletter, local print, noticeboards — can start this week
5.4 Prepare next community meeting agendaUNBLOCKED (logistics) — BLOCKED-BY-STREAM (needs steering group seated, task 0.3)Don’t run the meeting until the steering structure exists
5.5 Own the public FAQUNBLOCKEDWebsite already has FAQ; expand with stream outputs as they come
5.6 Enforce vocabulary standardsUNBLOCKEDOngoing operational discipline; steering group owns this
5.7 Run second community meetingBLOCKED-BY-STREAM (task 0.1 — steering group seated)Community needs to see the structure, not just intentions
5.8 Frame interest-level EOI updateBLOCKED-BY-STREAM (Stream 3 designs the questions; lawyer-reviewed before sending)No dollar bands in public/EOI forms until reviewed
5.9 Publish steering committee membership and decision logBLOCKED-BY-STREAM (task 0.1 — steering group seated)Transparency once the group exists

No internal research document yet. Outputs needed:

  • Updated EOI database (Billie has the ~68 names)
  • Skills and interest inventory from EOI list
  • Steering committee membership published once formed

Stream 6 — Operating Model & Business Plan

No primary document yet. Stream 6 is a synthesis stream — it waits on Streams 2, 3, and 4 for detailed model inputs. Related epics: EPIC-005 (governance architecture), EPIC-007 (due diligence and decision gates)

Task status:

TaskStatusNotes
6.1 Desktop research: local market and competitive landscapeUNBLOCKEDNo dependencies; can start immediately
6.2 Map operating options (pub, accommodation, co-working, events, mixed use)UNBLOCKEDDesktop research with rough revenue estimates
6.3 Draft staffing model vs Hospitality Award 2020UNBLOCKEDAward is public; site’s feasibility briefing has started this
6.4 Compare operator models (employed publican, lease, hybrid)UNBLOCKEDDesktop research; no dependencies
6.5 Compile regional Tasmanian pub turnover and operating dataUNBLOCKEDTourism Tasmania data + ATO benchmarks; site’s feasibility briefing started this
6.6 Draft path-to-profitability modelBLOCKED-BY-STREAM (Streams 2, 3, 4)Needs: Stream 2 structure decision, Stream 3 capital model, Stream 4 minimum viable works scope
6.7 Draft cash-flow forecast (purchase through year 1)BLOCKED-BY-STREAM (Streams 2, 3, 4)All figures illustrative until inputs available
6.8 Define go/no-go conditionsBLOCKED-BY-STREAM (all streams)Integration output for steering committee — Stage 1 exit gate

What it needs before it can produce meaningful output:

  1. Stream 2 structure decision (lawyer opinion + steering committee decision)
  2. Stream 3 capital model (both structure scenarios)
  3. Stream 4 minimum viable opening scope

Research Cell — Case Studies & Evidence

Related epic: EPIC-006 (case study and evidence base)

Task status:

TaskStatusNotes
R.1 Build verified precedent registerUNBLOCKEDSite briefings have started (Castlemaine, Sea Lake, Pleasant Hills, Hotel Theodore, Renmark, Mogumber); extend and verify
R.2 Label what’s analogous and what isn’tUNBLOCKEDNo dependencies; can run in parallel with R.1
R.3 Push verified findings to streamsUNBLOCKED — ONGOINGDistribute on demand as streams need them

What Needs Human Action Now

These cannot be resolved by further desk research or agent work:

PriorityActionStreamBlocks
1 — UrgentStream 0: Appoint authorised contact for the appointed receivers0Everything in Stream 1
2 — UrgentStream 0: Call steering-group formation meeting (0.1)0Stream 5 second meeting, EOI framing
3 — UrgentStream 1: Human browser check of commercialrealestate.com.au listing1Property status clarity
4 — This weekStream 1: Title search via Land Tasmania1Assumptions 6.2, 6.3; Stream 3 model
5 — This weekStream 1: Request the previous purchaser’s reports1Assumptions 6.8; Stream 4 material
6 — This weekStream 2: Fill placeholder fields in lawyer_brief_draft.md and send2All capital instrument design
7 — This weekStream 2: Check Tas Parliament bills register for liquor licensing reform2Employed-manager pathway analysis
8 — Low effortStream 3: Get current liquor licence fee schedule from Treasury Tasmania3Assumptions 6.12
9 — Low effortStream 3: Get APRA AMCOS and PPCA current tariff schedules3Assumptions 6.13

What Agents Can Do Next (No Human Dependency)

TaskOutputFeeds
Stream 6 task 6.1: Local market desktop researchCompetitive landscape memoStream 6 operating model
Stream 6 task 6.2: Operating options mapOptions map with rough revenue estimatesStream 6 operating model
Stream 6 task 6.3: Staffing model vs Hospitality AwardAward-compliant staffing draftAssumptions book 6.9, Stream 6 model
Stream 6 task 6.4: Operator model comparisonOperator model memoStream 6 operating model
Stream 6 task 6.5: Regional Tasmanian pub operating dataRevenue and cost benchmarksAssumptions book 6.20, Stream 6 model
Stream 4 task 4.4: Scope building condition assessmentBrief + indicative cost to commissionSteering group funding decision
Stream 4 task 4.5: BCA/DDA compliance researchCompliance requirements memoAssumptions book 6.7
Stream 3 task 3.3: Grant eligibility mapNon-distributing vs distributing grant landscapeAssumptions book 6.15, Stream 3 model
Stream 3 task 3.4: Capital instruments under Tasmanian lawCapital instruments memoStream 3 model, Stream 6 operating model
Stream 2 task 2.5: Interim entity researchOptions for interim legal capacitySteering committee decision 0.7
Research cell R.1/R.2: Castlemaine case study splitVerified vs hypothetical tableSite copy review, Stream 3

Critical Path (in dependency order)

Stream 0: Authorised contact appointed  [BLOCKED-BY-HUMAN]
  └─ Stream 1: receivers contact made  [BLOCKED-BY-HUMAN — task 0.4]
      └─ Stream 1: Property status confirmed
          └─ Stream 1: Title search
              └─ Stream 3: Capital model (both structure scenarios)
                  └─ Stream 6: Path-to-profitability

Stream 2: Lawyer brief sent  [BLOCKED-BY-HUMAN — placeholder fields]
  └─ Stream 2: Written legal opinion received
      └─ Steering committee: Structure decision (distributing/non-distributing)
          └─ Stream 3: Capital instruments designed
          └─ Stream 6: Operating model finalised

Stream 1: Physical access arranged  [BLOCKED-BY-HUMAN — task 0.4 + 1.1]
  └─ Stream 4: Independent building assessment commissioned
      └─ Stream 4: Minimum viable opening scope
          └─ Stream 6: Path-to-profitability

Parallel work that can start now (no human dependency):

Stream 2: Research tasks (2.1, 2.2, 2.3, 2.4, 2.5)  [UNBLOCKED]
Stream 3: Assumptions book + scenario modelling (3.1–3.5)  [UNBLOCKED]
Stream 4: Desktop tasks (4.4 scoping, 4.5 BCA/DDA research)  [UNBLOCKED]
Stream 5: EOI update, skills inventory, comms channels (5.1–5.3, 5.5–5.6)  [UNBLOCKED]
Stream 6: All desktop research tasks (6.1–6.5)  [UNBLOCKED]
Research cell: R.1–R.3  [UNBLOCKED]

Stage 1 exit gate: All three critical-path threads above need to deliver before the steering committee can answer the Stage 1 exit question: “Is there enough credible community support and enough plausible feasibility to spend money on formal Stage 2 due diligence?”


Gaps That Could Not Be Resolved Without Human Knowledge

The following items remain open after this sync pass. They require human input or action:

  1. GitHub issue cross-references — access to adrianwedd/bottom-pub-coop was not available at sync time. If issues exist that cross-reference stream tasks (especially Stream 1 property status, Stream 2 lawyer brief), those links are not captured here.
  2. Steering committee seats — named individuals — workplans.md names Lachlan (building seat) and Molly (legal/governance) as potential resources. Whether either has been conflict-checked or confirmed is unknown. The conflict-of-interest protocol (task 0.2) must be completed before seats are confirmed.
  3. Previous-purchaser reports retrieval — Billie mentioned access to the asbestos and building reports at the meeting. Whether these have been formally shared with the steering group is unknown. This is a Stream 4 prerequisite that requires a human to follow up.
  4. Property listing status — whether the Commercial Hotel is currently actively listed, under offer, or in a different stage of the receivership process is unknown. The 2–3 week window from the 11 May email may have passed. Human browser check (priority 3 above) is needed immediately.
  5. Interim entity decision — whether an interim entity (incorporated association) has been or should be formed to hold communications and receive EOI data before co-op registration is a steering committee decision. Stream 2 task 2.5 can research the options; the decision itself requires human sign-off.