Campaign archive

The working documents, preserved as found.

Between May and August 2026 a small group in Cygnet, Tasmania tried to work out whether the town could buy its pub as a co-operative. It couldn't — the offer was unsuccessful and the property went under contract to someone else. What's left is the apparatus: the registers, the checks, the unmade decisions and the eight-day sprint plan. This is that apparatus, with the private parts removed and everything else left alone.

56 documents · 12 sections · Tranches 1–2 Campaign concluded 13 Aug 2026 Every page carries its provenance
Why publish this

The value is the reasoning, not the result.

Most community campaigns leave behind a press release and a bank statement. This one ran on a written discipline: every claim entering a document was tagged as one of five things, and the tag decided how much weight it could bear.

FactAssumptionChoiceRiskTodo

That discipline produced things worth keeping: an assumptions register that records what would break if each belief was wrong; a risk register with a "materialised" section nobody filled in even after risk #1 came true; a case-study review that debunked the flagship precedent the original draft leaned on; an adversarial report in which an AI agent was told to attack the project's own finance language; a decision log that stayed empty next to a map of twenty-three decisions waiting to be made; and a critical path written with eight days on the clock that opens by admitting the money could not be raised in time.

The mistakes are left in. The tags are left in. Statuses read "Open" because they were open on the day. Two documents still say "not for public release" in their first line, because that is what they said. If you want the polished account, wait for the post-mortem. If you want to see how the sausage was actually made — the wrong assumptions, the corrections, the agent/human disagreements, the awkward working language — it is here.

How these pages were made — and what is not here

Nothing on these pages is a live document. Every one is a derived copy, authored from a private original that stays where it was, unedited. Each copy went through an automated scan for credentials, contact details, correspondence and negotiation language, then a full human read, before it is published. The frame at the top of every page records the original's title, date, phase, purpose and status, the source it came from, the publication treatment (substantially intact, archival frame or derived), what was changed and why, who prepared it and who reviewed it.

Held back, by rule: private correspondence, legal advice on the project's position, negotiation strategy, respondent-level community data, third-party documents, anything that could identify a private individual even with the name removed, and anything about who bought the pub — the working group does not know, and this archive names nobody. If a page seems to have a hole in it, that is usually why, and the page will say so.

Orientation

Start here. How large the private corpus actually was, what happened in the world outside the repository, and how these pages were cleared for publication.

  • The corpus map — what was actually in there Derived

    A computed inventory of the Git-tracked private working corpus behind a 35-page public website — every reproducible artefact classified by working area and by what happened to it at the publication boundary. The archive you are reading is the visible part; this is the shape of the whole.

    18 August 2026 · Archive publication (after the campaign concluded)
  • What actually happened — the campaign outside the repository Derived

    The repository was an instrument panel, not the campaign. This is the real-world sequence — meetings, a receivership, media, a listing with a three-week fuse, an offer, a loss — with the documents each event produced set alongside it.

    18 August 2026 · Archive publication (after the campaign concluded)
  • How this fossil was published Derived

    The publication boundary, described by the people who built it — the twelve never-publish categories, the fifteen-rule scanner that cannot approve anything, the rule-scoped waivers, the invariant that stops a preview claiming to be published, and the error every automated gate missed.

    15–18 August 2026 · Archive publication (after the campaign concluded)
Epistemics

The registers that carried the FACT / ASSUMPTION / CHOICE / RISK / TODO discipline, the protocol behind them, and the adversarial passes that checked the project against itself.

  • Assumptions register Intact

    Thirty tagged claims — what the campaign thought it knew, how sure it was, and what would break if it was wrong. The most transferable thing the project built.

    Seeded 18 May 2026; last revised 12 June 2026 · Stage 1 — Gauging interest
  • Capital-model safety report Intact

    Eleven flagged phrases and three priority fixes: what an agent found when told to attack the project's own finance language for leakage risk.

    18 May 2026 · Stage 1 — Gauging interest
  • Risk register Intact

    Fourteen risks, one of which came true. The register that never got its 'materialised' row filled in.

    Last updated 4 June 2026 · Stage 1 — Gauging interest
  • The evidence curation protocol Intact

    The rulebook underneath every register in this archive — the five claim statuses, how a claim entered the record, what it took to close a research question, and the explicit list of things desk research could not settle.

    22 May 2026 · Stage 1 — after the first community meeting
  • The gap analysis — what we knew we didn't know Intact

    A cross-stream audit of the project's own ignorance: the securities exposure, the unverified valuation and capex, the licensing pathway, the insurance nobody had scoped, and the volunteer capacity nobody had counted.

    May 2026 · Stage 1 — due diligence
Evidence

What happened when named precedents and local history were checked against primary sources: one debunked, several corrected, most confirmed but not analogous.

  • Case-study verification register Intact

    The first triage of the precedents: 'Remove until proven', 'Use only as broad inspiration', 'Verify before publication'.

    c. 18–20 May 2026 · Stage 1 — Gauging interest
  • Case-study validation report Intact

    The report that called the original operating model's economics 'spreadsheet astrology' and debunked its flagship precedent.

    c. 18–20 May 2026 · Stage 1 — Gauging interest
  • Case-study cleaned register Intact

    Fifty-seven precedent claims taken apart: 34 held, 5 were debunked, and two Cygnet hypotheticals had drifted into being read as Castlemaine facts.

    Last reviewed 19 May 2026 · Stage 1 — Gauging interest
  • The building — 1884 to now Intact

    A short history of the Commercial Hotel: who built it, what it was called, how it changed, and why a Victorian Georgian pub ended up on the heritage register.

    May 2026 · Stage 1 — evidence research
  • Feeding the whole corpus to a machine Derived

    Fifty-four documents loaded into a research tool that generated briefing papers, study guides, data tables, slide decks and three AI-hosted audio discussions about a community pub campaign. Useful for onboarding, dangerous as a source.

    May–June 2026 (last refreshed 12 June 2026) · Whole campaign
Feasibility & finance

The viability question and the money behind it — the feasibility study, the assumptions book, the capital stack, the grant landscape, and a rehearsed accountant.

  • The draft feasibility study Intact

    The whole viability question in one document — property, market, technical, legal and financial feasibility — written eight days before the deadline, with every load-bearing figure tagged FACT, REPORTED, ESTIMATE, CHOICE or STAGE 2, and a preliminary conclusion that refuses to conclude.

    24 June 2026 · Acquisition sprint (Stage 1, final fortnight)
  • The finance assumptions book Framed

    Every number the project ever used, with its source, its confidence label and what breaks if it is wrong. Eight hundred lines of it — and its own adversarial review flagged eleven phrasings as extractable, which were never fixed.

    18 May – June 2026 · Stage 1 — feasibility research
  • The capital stack — an indicative scaffold Intact

    Where the money would have had to come from: community shares, community loans, philanthropy, debt and grants, sized against a purchase price nobody knew. Explicitly a scaffold, never a model.

    24 June 2026 · Acquisition sprint (Stage 1, final fortnight)
  • The grants and community-finance scan Intact

    Every grant, fund and social-finance route the project could find that a community pub might plausibly use — with eligibility read carefully enough to rule most of them out, and the blockers that made the rest premature.

    May–June 2026 · Stage 1 — feasibility research
  • The market memo — who else is selling a drink in Cygnet Intact

    A hospitality market assessment of a town of about 1,500 people: the other venues, the cider and wine businesses, festival and tourism seasonality, and whether the town can support a third pub run on community capital.

    June 2026 · Stage 1 — operating model research
  • Rehearsing the accountant we never hired Intact

    The same experiment on the tax and accounting side — GST, DGR status, income-tax treatment of a co-operative, the mutuality principle, and what any of it means for a community pub. A simulation, labelled as one on every page.

    24 June 2026 · Acquisition sprint (Stage 1, final fortnight)
Legal & property

Co-operative structure, liquor licensing, heritage constraints, the title search, and the brief written for a solicitor who was never retained.

  • Legal structure and liquor licensing — the research brief Intact

    Which co-operative form, whether it can hold a liquor licence, where the securities boundary sits, and what an interim entity could lawfully do. The research that got as far as desk research can get, and stops precisely where legal advice has to start.

    18 May 2026 (maintained through June) · Stage 1 — due diligence
  • Liquor licensing reform — watching a bill that mattered Intact

    A short standing note tracking Tasmanian liquor-licensing reform, because the answer to 'can a co-operative hold the licence?' depended on law that was itself changing.

    May–June 2026 · Stage 1 — due diligence
  • Heritage constraints on an 1884 building Intact

    What it actually means to own a permanently registered heritage pub — which works need approval, which are exempt, what a Conservation Management Plan is for, and why nobody could scope the building work without getting inside.

    May 2026 · Stage 1 — due diligence
  • Is it even for sale? — tracking a property that wasn't listed Intact

    For a month the group had a rumour and no listing. This is the systematic check — every commercial portal, every hotel broker, the insolvency notices register — that established what was actually knowable.

    18 May 2026 (maintained to June) · Stage 1 — due diligence
  • The title search that changed the picture Derived

    Ten days after hearing the pub might sell, the group bought a title search. It reframed the sale from a clean receivership disposal into a multi-party creditor problem — and it is the clearest example in the archive of desk research paying for itself.

    19 May 2026 · Stage 1 — due diligence
  • Rehearsing the lawyer we never hired Intact

    An AI was asked to write the advice a careful Tasmanian solicitor might give to the project's brief — explicitly as a simulation, explicitly not to be relied on — so the group could find the gaps in its own questions before paying for an hour of the real thing.

    24 June 2026 · Acquisition sprint (Stage 1, final fortnight)
  • The legal questions that were never answered Intact

    A single register of every unresolved legal question across licensing, structure and property — the honest list of what the project did not know when it ran out of time.

    May–June 2026 · Stage 1 — due diligence
  • Source annex — Tasmanian liquor licensing Intact

    The primary-source trail behind the licensing research: statutes, sections, regulator guidance and reform material, with current law kept separate from proposals.

    June 2026 · Stage 1 — legal handoff preparation
  • Source annex — co-operative structure Intact

    The same trail for the structure question: distributing versus non-distributing co-operatives, active membership, the securities boundary, and the interim-entity options.

    June 2026 · Stage 1 — legal handoff preparation
Governance & operations

The organisation the group designed before it existed: working groups, steering pack, operating models, staffing, and the policies underneath them.

  • The working-group architecture Intact

    Seven streams, their scopes, their outputs and the boundaries between them — the organisation the project designed before it had a legal entity or a single elected officer.

    20 May 2026 · Stage 1 — after the first community meeting
  • The governance operations runbook Intact

    How meetings were called, how decisions got recorded, how conflicts were declared, and how an urgent decision could be made between meetings without anyone later arguing about whether it was made.

    May–June 2026 · Stage 1 — governance formation
  • The steering pack — governance templates Derived

    Five governance instruments written for a committee that did not exist yet: a first-meeting agenda, a conflict-of-interest declaration, a decision log, a risk register and a source register. Lift-and-reuse infrastructure for the next community group.

    20 May 2026 · Stage 1 — governance formation
  • Accessibility, inclusion and safeguarding policy Intact

    A community pub that could not be entered by everyone in the community would have failed on its own terms. The policy written to stop that happening, including the safeguarding obligations nobody enjoys writing.

    June 2026 · Stage 1 — governance formation
  • What a pub could actually be Intact

    Every use the building and site could be put to — core pub, kitchen, accommodation, events, garden, multipurpose space — with indicative revenue contribution and the constraints on each. Imagination mapped; viability deliberately not yet assessed.

    June 2026 · Stage 1 — operating model research
  • Employed, tenant, or hybrid — who actually runs it Intact

    The three ways a community-owned pub can be operated, compared on control, risk, capital, licence-holding and mission integrity — and why the choice could not be made until the legal structure was settled.

    June 2026 · Stage 1 — operating model research
  • The staffing model — what it costs to open the doors Intact

    Award classifications, penalty rates, a minimum viable opening team and the wage bill underneath it. The least romantic document in the archive and one of the most important.

    June 2026 · Stage 1 — operating model research
Community data

What aggregate community-capacity data looked like, how people were invited to contribute, and the data-hygiene lesson it carried.

  • The intake runbook — what happens after someone says yes Intact

    Four hundred lines on the unglamorous half of community organising: how an expression of interest was received, acknowledged, triaged, stored, consented and followed up, and how to do that without losing anyone or misusing their data.

    June 2026 · Stage 1 — community engagement
  • The contribution ladder — every way to help that isn't money Intact

    From 'stay on the list' to 'join the board' — the deliberate design of a participation path, built so that people who could not contribute capital were not sorted into a lesser category.

    June 2026 · Stage 1 — community engagement design
  • EOI & skills inventory (24 June 2026) Derived

    What the community's expressed capacity looked like in aggregate five weeks after the town meeting — and the deduplication and consent lessons that came with it. A clean public copy; the respondent-level source stays private.

    24 June 2026 · Acquisition sprint (Stage 1, final fortnight)
  • Approaching major supporters — the ethics first Intact

    How to ask people with money for help without turning neighbours into targets: tiers of contribution beyond cash, public-record research only, and a hard rule against approaching anyone through a private relationship.

    24 June 2026 · Acquisition sprint (Stage 1, final fortnight)
  • The supporter approach kit Intact

    The practical half of the strategy: what to send, what to say, what to never say, and the disclosure rules for a group that had no legal entity and could not accept money.

    24 June 2026 · Acquisition sprint (Stage 1, final fortnight)
Decisions

The decision machinery — the dependency map of unmade choices, and the log designed to record them, published for what it is.

  • Choice map Framed

    Twenty-three decisions nobody had made yet, wired together by what blocked what. Published with the graph source and the register intact.

    Updated 22 May 2026 · Stage 1 — Gauging interest
  • Decision log — the mechanism, not the minutes Derived

    The steering committee's decision log as it exists in the repository — a governance template with an empty table. Published honestly as the mechanism that was designed, not as evidence of decisions recorded.

    Template drafted c. 18–20 May 2026; working file last touched 22 May 2026 · Stage 1 — Gauging interest
  • The dependency map — deprecated after one day Intact

    A cross-link of every internal document to its stream, its open questions and what needed a human — written on 18 May, marked DEPRECATED on 19 May, and never updated again. The thing that replaced it froze too.

    18 May 2026 · Stage 1 — after the first community meeting
Operations

The eight-day sprint plan against a hard deadline, the due-diligence matrix, the guardrail checklist, and the workstream board.

  • Critical path — eight days to the EOI deadline Derived

    The sprint plan written with eight days left on the clock. The dependency graph, the phase gates and the five ways it could fail — with the negotiating posture and the people taken out.

    24 June 2026 · Acquisition sprint (Stage 1, final fortnight)
  • Due-diligence matrix Intact

    Twenty-four questions the project knew it had to answer before anyone could responsibly buy a pub. Most were still open at the end.

    c. 18–20 May 2026 · Stage 1 — Gauging interest
  • EPIC board — the seven proposal workstreams Derived

    How the project broke a flawed 40-page proposal into seven bounded workstreams, each with a problem statement, tasks and acceptance criteria — and the board that tracked them, frozen at its last update.

    EPICs drafted c. 18–20 May 2026; board last updated 4 June 2026 · Stage 1 — Gauging interest
  • Guardrail screening checklist Intact

    The rulebook turned into a grep list: forbidden phrases, safe rewrites, and the compliant-usage carve-out that stopped the checklist from flagging its own safety language.

    24 June 2026 · Acquisition sprint (Stage 1, final fortnight)
Communications

How the project controlled its own language: the binding public language sheet, and the content strategy behind what the site was allowed to say.

  • The public language sheet — what we were allowed to say Intact

    A binding, one-page standard for everyone speaking on behalf of the project: the phrases that were forbidden, the phrases to use instead, and what to say when someone asked a question the project could not answer.

    20 May 2026 · Stage 1 — governance formation
  • How to talk to a town about buying its pub Intact

    Audience by audience — locals who drink there, locals who never did, the diaspora, the sceptics — what each needed to hear, where they'd hear it, and what the project was not allowed to say to any of them.

    May–June 2026 · Stage 1 — communications planning
Machinery

The engine room — the heterogeneous agent fleet, the constraints that made it useful, the state-synthesis machinery, and the technical infrastructure under the site.

  • The agent ecology — five systems, none of them in charge Derived

    A heterogeneous fleet of AI systems did substantial research, drafting and review on this project. This is what each was actually used for, where they caught each other, where they were confidently wrong, and the constraint architecture that made them useful rather than dangerous.

    18 August 2026 · Whole campaign (May–August 2026)
  • The constraint architecture — the actual prompts Derived

    Six representative agent contracts and task prompts, reproduced exactly as they were written. This is the layer that made a fleet of unreliable systems produce a defensible corpus — and it is much shorter and blunter than people expect.

    May–June 2026 · Whole campaign (May–August 2026)
  • The state machinery, and the day it said "unchanged" Derived

    The project built automation to answer "what is the current state?" and "has the property been listed?". It ran for three months, 91 checks, and never once reported a change — including on the day the pub was listed for sale. This is why.

    19 May – 18 August 2026 · Whole campaign
  • The changelog — a hundred days, in order Intact

    Day by day, what changed and why — written as prose rather than commit messages. The single best record of how the project's thinking moved, including the days it talked itself out of something.

    9 May – 28 June 2026 · Whole campaign
  • The workplans — everything that would have had to happen Intact

    Seven streams of work broken into numbered tasks with dependencies, written from the first community meeting. A map of the whole job, most of which was never done.

    20 May 2026 · Stage 1 — after the first community meeting
  • What was actually running underneath Derived

    A 22-page site with 13 rendered briefings, a strict content-security policy, three Worker deployments, a database, Zero Trust on two protected areas, and a build that refused to ship copy the project had banned. Described, not dumped — the runbooks stay private.

    May–August 2026 · Whole campaign
Post-mortem

What was learned, what would be done differently, and what the group thinks it got right despite losing.

  • Post-mortem — we lost, and this is why Derived

    The working group's own account of why a community co-operative could not buy a pub from a mortgagee in possession — four reasons, none of them about enthusiasm — and what it would tell the next town that tries.

    18 August 2026 · After the campaign concluded (13 August 2026)
Intact — substantially intact
The text is the original's, with any redactions marked in-line and listed on the page. Even so, it was scanned and read in full before publication; "intact" is a description of the outcome, not a shortcut.
Framed — archival frame
As above, but the original needed more context than a redaction note gives — usually because it contains strategic material that reads differently outside the room it was written for.
Derived
A new document authored from one or more originals. Structure and reasoning are preserved; people, negotiating posture and respondent-level data are not. The page lists every non-trivial decision.
Tranches 1–2 · published 19 August 2026 Historical working documents · not an active proposal